Chapter 10

Questions

1. Determine the schedule and cost variance for a project that has an actual cost at month 20 of $750,000, a scheduled cost of $600,000 and an earned value of $700,000.

2. Determine the schedule variance, cost variance, SPI, CPI, and CSI for a project that has an actual cost at month 12 of $90,000, a scheduled cost of $100,000 and an earned value of $120,000.

3. A software development project at day 60 exhibits an actual cost of $300,000 and a scheduled cost of $375,000. The software manager estimates a value completed of $300,000. Determine the schedule variance, cost variance, SPI, CPI, and time variance for the project.

4. A project to develop a county park has an actual cost in month 24 of $240,000, a planned cost of $290,000, and a value completed of $80,000. Determine the schedule variance, cost variance, SPI, CPI, and CSI for the project.

Need your ASSIGNMENT done? Use our paper writing service to score better and meet your deadline.


Click Here to Make an Order Click Here to Hire a Writer